5 TON PLANT RUNNING SUCCESSFULLY IN TAMILNADU06/01/2015
5 TON PLANT RUNNING SUCCESSFULLY IN TAMILNADU

4th plant in Tamilnadu with 5-TPD capacity installed and running successfully in Thoothukudi, Tamilnadu. April-2015

10 TON PLANT RUNNING SUCCESSFULLY IN M.P16/04/2015
10 TON PLANT RUNNING SUCCESSFULLY IN M.P

9th plant in Madhya Pradesh with 10-TPD capacity installed and running successfully in Katni, Madhya Pradesh.- March 2015

10 TON PLANT RUNNING SUCCESSFULLY IN TELANGANA18/04/2015
10 TON PLANT RUNNING SUCCESSFULLY IN TELANGANA

6th plant in AP- Telangana with 10-TPD capacity installed and running successfully in Kodad, Nalgonda, Telangana- March-2015

TWO 10 TON PLANTS INSTALLED AND RUNNING IN HARYANA01/02/2015
TWO 10 TON PLANTS INSTALLED AND RUNNING IN HARYANA

11th and 12th plants in Haryana with 10-TPD capacity installed and running successfully in Yamunanagar, Haryana.- Dec. 2014

10 TON PLANT INSTALLED AND RUNNING IN M.P25/12/2014
10 TON PLANT INSTALLED AND RUNNING IN M.P

8th plant in Madhya Pradesh with 10-TPD capacity installed and running successfully in Badnawar (2nd-Repeat), Madhya Pradesh.- Dec. 2014

10 TON PLANT RUNNING IN HARYANA12/02/2014
10 TON PLANT RUNNING IN HARYANA

10th plant in Haryana with 10-TPD capacity installed and running successfully in Hisar, Haryana.- Oct. 2014

10 TON PLANT RUNNING IN UTTAR PRADESH09/11/2014
10 TON PLANT RUNNING IN UTTAR PRADESH

3rd plant in Uttar Pradesh with 10-TPD capacity installed and running successfully in Greater Noida, Uttar Pradesh. Sept-2014

10 TON PLANT RUNNING IN UTTARAKHAND09/11/2014
10 TON PLANT RUNNING IN UTTARAKHAND

1st plant in Uttarakhand with 10-TPD capacity installed and running successfully in Jaspur, Uttarakhand. Aug-2014

10 TON PLANT RUNNING SUCCESSFULLY IN TAMILNADU15/05/2014
10 TON PLANT RUNNING SUCCESSFULLY IN TAMILNADU

3rd plant in Tamilnadu with 10-TPD capacity installed and running successfully in Coimbatore, Tamilnadu. May-2014

10 TON PLANT RUNNING SUCCESSFULLY IN A.P.14/03/2014
10 TON PLANT RUNNING SUCCESSFULLY IN A.P.

5th plant in Andhra Pradesh with 10-TPD capacity installed and running successfully in Miyapur, Hyderabad.

TWO 10 TON PLANTS RUNNING IN ANDHRA PRADESH14/03/2014
TWO 10 TON PLANTS RUNNING IN ANDHRA PRADESH

3rd and 4th plants in Andhra Pradesh with two 10-TPD capacity installed and running successfully in Masaipet, Andhra Pradesh.- March 2014

5 TON PLANT RUNNING SUCCESSFULLY IN HARYANA14/03/2014
5 TON PLANT RUNNING SUCCESSFULLY IN HARYANA

9th plant in Haryana with 5-TPD capacity installed and running successfully in Karnal, Haryana.- Feb. 2014

10 TON PLANT RUNNING SUCCESSFULLY IN MAHARASHTRA18/01/2014
10 TON PLANT RUNNING SUCCESSFULLY IN MAHARASHTRA

5th plant in Maharashtra with 10-TPD capacity installed and running successfully in Navapur, Maharashtra.

10 TON PLANT RUNNING SUCCESSFULLY IN M.P23/11/2013
10 TON PLANT RUNNING SUCCESSFULLY IN M.P

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste TYRE Pyrolysis Plant seting up in Madhya Pradesh. The plant is running successfully.

10 TON PLANT RUNNING SUCCESSFULLY IN A.P23/11/2013
10 TON PLANT RUNNING SUCCESSFULLY IN A.P

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste TYRE Pyrolysis Plant seting up in Andra Pradesh. The plant is running successfully.

10 TON PLANT RUNNING SUCCESSFULLY IN ASSAM13/11/2013
10 TON PLANT RUNNING SUCCESSFULLY IN ASSAM

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste TYRE Pyrolysis Plant seting up in ASSAM. The plant is running successfully.

10 TON PLANT RUNNING SUCCESSFULLY IN ABU ROAD29/10/2013
10 TON PLANT RUNNING SUCCESSFULLY IN ABU ROAD

Divya International provides pyrolysis process solution on turnkey basis and recently installed plant in Abu road in Oct- 2013 and it is running successfully.

10 TON PLANT INSTALLING IN AASAM10/09/2013
10 TON PLANT INSTALLING IN AASAM

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste TYRE Pyrolysis Plant seting up in AASAM.

10 TON PLANT INSTALLING IN ABUROAD10/09/2013
10 TON PLANT INSTALLING IN ABUROAD

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste TYRE Pyrolysis Plant seting up in aburoad.

10 TPD Plant Installed in Mathura (U.P)30/08/2013
10 TPD Plant Installed in Mathura (U.P)

Our relentless commitment towards our customer we have installed 10 tons tyre recycling pyrolysis plant at Mathura distt. (U.P) through the reference of our existing client.

10 TPD Plant In Patna ( Bihar )30/08/2013
10 TPD Plant In Patna ( Bihar )

Divya International keep focusing in quality and best after sales service, by this ethic divya international spred his wings to all over the india. the most advance 10 Ton waste Recycling Pyrolysis Plant set up in Patna ( Bihar).  this plant running smoothly.

Installation of pyrolysis plant in Maharashtra04/12/2013
Installation of pyrolysis plant in Maharashtra

4th plant in Maharashtra of 5-TPD capacity is going to installed in Gondia (Nagpur), Maharashtra.

Installation of pyrolysis plant in Andhra Pradesh15/03/2013
Installation of pyrolysis plant in Andhra Pradesh

10-ton capacity plant is going to installed in Prakasam, Andhra Pradesh with many advance features & facilities including in it.

Installation of pyrolysis plant in Hisar15/03/2013
Installation of pyrolysis plant in Hisar

"Confidence comes from discipline and training." As per our Hisar client's quote "Quality pyrolysis machinery is the one part of Divya's success, the other part is the what knowledge & training they inculcate during the operator training sessions & after sales support which they provide. This helped me to generate confidence in pyrolysis field." With this confidence our Hisar client has installed his 2nd plant of 5-TPD in Haryana.

Installation of pyrolysis plant in Bcchiwara15/03/2013
Installation of pyrolysis plant in Bcchiwara

"Quality is never an accident"; it is always the result of high intention, sincere effort, intelligent direction and skillful execution; it represents the wise choice of many alternatives. Our quality focused approach has got us our 8 repeat order dispatch for Rajasthan, Bicchiwara. Two 5-TPD capacity plant is going to install parallelly.

Installation of pyrolysis plant in Karnal15/03/2013
Installation of pyrolysis plant in Karnal

"Quality is not an act, it is a habit." That's what we are upto. Our constant zest to provide our clients with quality tyre pyrolysis machinery has made possible to install our 8th plant in Haryana (& still counting more).

Installation of pyrolysis plant in Mumbai15/03/2013
Installation of pyrolysis plant in Mumbai

3rd plant in Maharashtra of 12-TPD capacity is going to installed in Wada (Thane), Mumbai.

Installation of pyrolysis plant in Ajmer15/03/2013
Installation of pyrolysis plant in Ajmer

5-ton capacity plant is going to installed in Rajasthan Ajmer.

Installation of Pyrolysis plant in Tamilnadu15/03/2013
Installation of Pyrolysis plant in Tamilnadu

2nd plant in south & Tamil of 12-TPD capacity is going to installed in Tamil Nadu, Theni with advance roller system & reactor cooling system.

Installation of pyrolysis plant in Chennai15/03/2013
Installation of pyrolysis plant in Chennai

Finally our 1st plant in south of 10-TPD capacity is going to installed in Tamil Nadu, Chennai.

Installation of pyrolysis plant in Hassi15/03/2013
Installation of pyrolysis plant in Hassi

Providing quality & service has been essence of Divya International since it's ineption & these quality of our's has build up the trust in our clients in Haryana. Because of this we are going to install our 6th plant in Haryana from total 25 plants installed across all over India.

6 plants in Haryana itself & counting more........   

Installation of pyrolysis plant in Rohtak15/03/2013
Installation of pyrolysis plant in Rohtak

"Quality speaks louder than words" that's what we are proving true. Repeat orders continues, our first client in Jind, has given the repeat order of 5-TPD capacity plant which is going to installed in Rohtak, Haryana.

Installation of pyrolysis plant in Bicchiwara15/03/2013
Installation of pyrolysis plant in Bicchiwara

10-ton capacity plant is going to installed in Rajasthan Bichhiwara with many advance features & facilities including in it.

MOU signed with "Sage Informatics Pvt. Ltd."10/02/2012
MOU signed with "Sage Informatics Pvt. Ltd."

Divya International has given authorized franchisee to Sage Informatics Pvt. Ltd for the territory of Southern Africa region which include the following countries- South Africa, Lesotho, Botswana, Malawi, Swaziland, Zambia, Zimbabwe, Madagascar, Mauritius, Angola, Nambia, Republic of Congo, Mozambique & Seychelles.

Installation of pyrolysis plant in Abu Road15/03/2013
Installation of pyrolysis plant in Abu Road

We just don't guide but also make businessmen. With our guidance & knowledge youths have come up & install 5-tons plant in Rajasthan, Abu Road in June 2012. that is working very smoothly.....

Installation of Pyrolysis-Plant in Haryana29/10/2013
Installation of Pyrolysis-Plant in Haryana

Our uncompromising quality standards, unparalleled services and individual attention have helped us to achieve our corporate objective of total customer satisfaction & by installing second 5-TPD capacity machinery of the same client in Sonepat within 6 months resembles that. Plant setup in June 2012.

Pyrolysis plant installed in Kolhapur15/03/2013
Pyrolysis plant installed in Kolhapur

Our second plant install in Maharashtra, Kolhapur. Plant setup in May 2012.

Pyrolysis plant installed in Bichhiwada, RJ15/03/2013
Pyrolysis plant installed in Bichhiwada, RJ

Services what we provide to our client gives us the business. Our 5-ton machinery install in Rajasthan, Bichhiwada. Plant setup in May 2012.

Pyrolysis plant installed in Billaspur, CG15/03/2013
Pyrolysis plant installed in Billaspur, CG

Our 3rd machinery installed in Chattisgarh, Billaspur. Plant set-up in April 2012.

2nd pyrolysis plant installed in Chattisgarh, Durg15/03/2013
2nd pyrolysis plant installed in Chattisgarh, Durg

Our uncompromising quality standards, unparalleled services and individual attention have helped us to achieve our corporate objective of total customer satisfaction & by installing second 5-TPD capacity machinery of the same client in Durg within 6 months resembles that. Plant setup in April 2012.

Pyrolysis plant installed in Haryana, Hisar15/03/2013
Pyrolysis plant installed in Haryana, Hisar

Our 3rd plant installed in Haryana, Hisar. Plant set-up in March 2012.

Pyrolysis plant installed in Maharashtra Jalgoan29/04/2013
Pyrolysis plant installed in Maharashtra Jalgoan

Our first plant in Maharashtra, Jalgoan. Plant setup in Feb 2012.

Pyrolysis plant installed in Jaipur, Rajasthan15/03/2013
Pyrolysis plant installed in Jaipur, Rajasthan

Our relentless commitment towards our customer we have installed 12 tons machine at Jaipur, Rajasthan in Feb 2012 through the reference of our existing client.

One of the most the awaited & the biggest project07/05/2012
One of the most the awaited & the biggest project

Our team has given the breakthrough in the pyrolysis field in India by designing & installing two 12-tons Plants parallely in Indore in Jan 2012. A start of year with a bang.

Pyrolysis plant installed in Sonepat, Haryana29/04/2013
Pyrolysis plant installed in Sonepat, Haryana

At the end of the year 2011 we have installed our 8th machine at Sonepat, Haryana in Dec 2011.

Pyrolysis-Plant installed in Gujarat, Oct 201129/10/2013
Pyrolysis-Plant installed in Gujarat, Oct 2011

Installation of 5 TPD in Gujarat in Oct 2011.

Pyrolysis Plant installed in Durg, Chattisgarh29/10/2013
Pyrolysis Plant installed in Durg, Chattisgarh

Our team continues to deliver quality & services which our customer need. With this we had installed our 1st project in Chattisgarh at Durg in Sept 2011.

Pyrolysis plant installed in Maharashtra Jalgoan

Our first plant in Maharashtra, Jalgoan. Plant setup in Feb 2012.